Location
New South Wales, Australia
Completion
2024-11
Service Type
FCR · FCAS
Capacity
50MW / 100MWh
50MW / 100MWh
System Capacity
≤180ms
Response Time
AUD 8.2M+
Annual FCAS Revenue
99.4%
Availability
The Problem to Solve
The NEM grid was experiencing increasing frequency volatility due to rapid solar and wind penetration. Traditional thermal generators could not ramp fast enough to maintain the 50Hz ±0.5Hz operating band during sudden generation or load events. The client needed a solution that could be prequalified for FCAS markets and deliver consistent, auditable performance data.
Our Approach
We deployed 25× 2MWh battery containers arranged in 5 rows of 5, each with an integrated 2MW PCS unit. The EMS platform monitors NEM frequency at 10ms intervals and dispatches power symmetrically within 180ms. The system is connected to AEMO via a dedicated fiber link and interfaces directly with the SCADA system for automated dispatch and performance reporting.
Technical Specifications


Measurable Results
- System achieved full FCAS prequalification within 3 weeks of commissioning
- Response time consistently 180ms — 10% faster than market requirement
- Annual FCAS revenue of AUD 8.2M+ in first operating year
- System availability >99.4% over 12-month operating period
- Zero unplanned outages; two scheduled maintenance windows completed on time